 Above: Laying the Main Trunk sewer at
Ynystawe, to the north of Swansea. |
In the summer of 1907, an outfall off Mumbles head was quickly accepted
as the ideal spot for discharge. Such was the size and cost of the scheme that it took a
further 10 years for other items such as the nature of the sewers and their size and
placing to be decided. Chief amongst the concerns was designing in sufficient future
proofing, so that the scheme would accommodate projected expansion and building
across the still growing Borough of Swansea. The central
element of the scheme was the main trunk sewer which ran over eleven miles through the
Borough from Clydach in the north running down the side of the river, around the sea front
and ending in a series of large storage tanks under Mumbles Head. Once complete, all the
older troublesome outlets into the river could be diverted into the main trunk and thence
to the new outfall at Mumbles. Careful planning and engineering ensured a fall of 71 feet
from the head of the sewer at Clydach to the outfall pipe at Mumbles. A 40 mile network of
subsidiary sewers connected the residential districts to the trunk sewer.
For its time the Main Drainage scheme was very
advanced. Although the difficulties of designing effective sea outfalls had yet to be
appreciated, the designers of the scheme tried to anticipate many problems. One of the
most unsavoury problems with the Tawe outfalls was that floating matter such as faeces,
balls of fat and other organic matter could not be broken down. The river was perennially
full of such material which also found its way onto the beach. Put simply, whatever was
put down toilets flowed directly into the river, or alternatively, it would contribute to
various blockages in the sewers. The flow in the new sewer was designed to be fast enough
to prevent blockage, and at the Mumbles end of the sewer, a series of screens and settling
chambers removed large bodies down to a size of half an inch and also allowed heavy matter
such as pebbles to drop out of the flow before they could do any damage to the system.

Once screened the sewage was to be stored in a series of long
thin storage tanks under Mumbles Hill. Approximately 7 ½ million gallons of sewage could
be stored within the tanks (sufficient capacity to comfortably accommodate the sewage
generated by 250,000 people, at least using 1920s water consumption habits!). The stored
sewage would be released into the sea at the appropriate state of the tide (i.e. when its
going out) through the sea outfall pipes approximately 220 yards offshore from the Mumbles
lighthouse.
With the completion of the scheme, the relief on the River Tawe
was swift. Although the river still had to cope with massive amounts of industrial
pollution (primarily heavy metals and associated toxins), the aesthetic quality of the
water was significantly improved. The scheme was widely recognised as a resounding
success. It had not only solved the sewerage problem, but it had over many years provided
much needed employment for many local men in the greatest years of the Depression.
One of the issues that the plagued the early sewerage schemes was
the problem of storm water. Heavy rainfall would flood streets, swamp drains and inundate
the town sewers causing unpleasant overflows or even damaging the system. The main
drainage scheme tried to take this problem into account but still suffered from
overloading during heavy rainfall events which, at times, resulted in the overflow of
sewage on to the beach Whilst this was acceptable in the immediate post-war years, such
incidents are now considered unacceptable along with the practice of releasing untreated
sewage into the bay.
Swansea has been served by the main drainage scheme since its
completion in the late 1930s to the present day. Only now, with the completion of Welsh
Waters flagship treatment works on Fabians Way on the east side of Swansea
Bay, that a radically new approach to Swanseas sewerage problem has emerged. |